Buying Consulting

How to Write Terms of Reference for a Consultancy Assignment in Mauritius

Terms of reference decide the selection method, how proposals are scored and what the contract buys. What the Procurement Policy Office guidance asks for, a section-by-section structure, and the rule that stops the author bidding. Our interest is disclosed.

What terms of reference have to contain

SectionWhat it statesWhat goes wrong when it is missing
A structure for terms of reference built from the definition in a Mauritian consultancy RFP of 15 October 2025. The third column is our experience of what follows when a section is left thin.

The selection method depends on how precise the terms can be

  • Quality and Cost Based Selection (QCBS). Quality and price both scored. Needs precise terms of reference.
  • Quality Based Selection (QBS). Quality alone, then negotiation with the highest ranked. The guide reserves it for “complex or highly specialized assignments for which it is difficult to define precise Terms of Reference”, assignments with very large downstream impact, and work that can be done in substantially different ways.
  • Fixed Budget Selection (FBS). Only when the assignment “is simple and can be precisely defined and when the budget is fixed”.
  • Least Cost Selection (LCS). For assignments “of a standard or routine nature”, the guide’s examples being audits and engineering design of non-complex works.

How the proposals will be scored

CriterionPoints out of 100, as the guide suggests
Table 3.1 of the PPO Evaluation Guide (Consultancy Services), 27 July 2012, read 1 October 2026. The guide notes the actual weights may be adjusted to the assignment and must be stated in the RFP.

Six checks before the terms of reference go out

  1. 01Name the decision the work supports. If the objective does not name a decision, a board paper or a policy, firms will each invent one.
  2. 02Write the exclusions. What is out of scope is the sentence that prevents the variation order.
  3. 03Date every deliverable. Payment milestones should attach to something you can hold in your hand.
  4. 04List your own inputs. Data, access, counterpart staff and approvals, with who provides each. The RFP format asks bidders to comment on these, so state them first.
  5. 05Describe the team you expect, not a headcount. The guide puts most weight on staff competence; tell bidders which competences matter.
  6. 06Pick the selection method last. Once the document is written, ask honestly whether it is precise enough for QCBS. If not, it is a QBS assignment.

The author of the terms of reference should not bid

Common questions

01How do you write terms of reference for consultancy services in Mauritius?
02What selection methods can a Mauritian public body use for consultants?
03What is the minimum technical score in a consultancy evaluation?
04Can the consultant who wrote the terms of reference bid for the assignment?
05Do the terms of reference become part of the contract?
Discuss a mandate

If this describes the problem in front of you, the next conversation is the useful one.

Enquiries are handled in confidence. We respond at principal level within one business day.

Continue reading